CONSTRUCTION OF A MULTI-PURPOSE HALL.
I. LOCATION: Lassin, Noni Sub Division, North West Province, Cameroon.
II. EXECUTING Body: Noni Women’s Association (NWA).
III. DURATION: One Year.
IV. CONTENT.
Lassin is 44Km from Kumbo which is the Divisional Headquarters of Bui Division,
in the North West Provine of Cameroon. Lassin is made up of 7000 inhabitants
from divergent ethnic origins such as the Nonis who are the majurity, Fulanis,
Haoussas, and Wimbums alongside other anonymous individual.
Considering the cultural
context of Lassin which is male-dominated, Noni Women’s Association (NWA) has
decided to take upon this initiative as a way of self-help development vis-à-vis
their problems. Noni Women are looked upon as objects or commodities to their
husbands whereby everything they do is considered their husbands property, but,
we intend to detach ourselves from this male-dominated custom.
This multi-purpose hall is
geared towards realizing women’s activities at two levels. The first level is
that, this hall will be a co-operative centre geared towards storing and marketing
agricultural produce. The second level is that of using this hall as a training
centre vis-à-vis sex education, secondary ship, farming techniques, life skills
and just to cite a few.
Lassin Women have contributions
in kind and in cash to offer vis-à-vis this construction project. In kind, voluntary
labour will be offered by some village youths (girls and boys) for the entire
construction project. This volunteer work will be subsequently …………in the budget
of this project. Whereas in cash, NWA has 2 000 000 CFAF to offer vis-à-vis
this project.
2. The Objectives.
This construction project
will be oriented towards the following objectives:
i. Co-operative activities: Storing and
marketing of agricultural produce.
ii. Provision of training course on sex education
hence family planning, domestic science, family welfare, farming methods to
drop out school girls.
iii. Cultural animation activities (community development
initiatives).
iv. Promotion of self-employment skills for
young girls.
The beneficiaries of this project can be categorized as follows:
Young girls.
Women.
Interested village association members.
The project will be executed by a follow-up committee of experienced members
alongside a recognized and a reputable construction firm. This follow-up committee
shall mobilize resources in kind and in cash geared towards the realization
of this project.
Furthermore, this committee
shall procure the resources necessary for this project by using transparent
and accountable standards. Purchased materials must be co-signed by all committee
members.
We equally want to acknowledge
the fact that work has started owing to the fact that land has been procured
and then reserved for this project.
NWA has equally saved some money which is 2 000 000CFAF coupled with volunteer
service, the entire NWA contribution can rise to 4 000 000CFAF for the whole
period of the construction process.
Upon implementation of this
project, the following results shall accrue:
The standard of living for Noni Women will rise.
Unwanted pregnancies will drop.
Self-employment will be on the increases.
Rural exodus will drop
Prostitution will equally drop.
Gender equity will be on the increase.
Communal spirit will be enhanced.
The fight against AIDS will be ensured.
BILL OF QUANTITIES AND ESTIMATE FOR THE PROPOSED NONI WOMEN ASSOCIATION LASSIN BRANCH.
ESTIMATE MATERIALS REQUIRE FOR THE PROJECT.
Materials |
Quantity |
Cost CFA |
Remarks |
Site (land) |
25: 40 x 14:12 |
1, 950, 000 |
|
Excavation |
25: 40 x 14:12 |
50, 000 |
|
Stones |
1 0 Cubic m |
300, 000 |
Community contribution |
Blocks sun dry |
4, 000 |
1, 200, 000 |
Community contribution |
Sand: Sharp/soft |
2 tones |
100, 000 |
Community contribution |
Iron rods: |
Q6 85 |
127, 500 |
Community contribution |
Iron rods: |
Q8 130 |
234, 000 |
|
Iron rods: |
Q10 10 |
25, 000 |
|
Binding wire |
12 rolls |
25, 000 |
|
Cement |
200 |
1, 200, 000 |
|
Concrete work |
|
500, 000 |
|
Masonry |
|
1, 000, 000 |
|
Roofing -Timber |
|
450, 000 |
Community Contribution |
Zinc 2m |
195 sheet |
585, 000 |
|
Zinc 3m |
117 sheet |
645, 000 |
|
Transport Zinc |
9 sheet |
135, 000 |
|
Carpentry |
|
1, 500, 000 |
|
Electricity |
|
300, 000 |
|
Painting / Deco |
|
910, 000 |
|
Metal work |
|
225, 000 |
|
Plumbing |
|
350, 000 |
|
Glazing |
|
250, 000 |
|
Contingences 20% |
|
2, 412, 300 |
|
Labour |
|
1, 809, 225 |
|
|
|
Grand Total |
16, 283, 025 |